How do I add the same holidays to more than one project without having to do it all by hand?AA-00605IntroductionMany integrators manage multiple projects. Most projects will have the same basic set of holidays. Adding them one by one in each project is time-consuming at best. The integrator can import the same basic holidays into each project he/she manages instead.
ProcedureCreate the Holidays and Export the All Holidays group
Import the Holiday Group into the new project
At this point, you will see that there are three (3) holiday groups: No Holidays, All Holidays, and the holiday group you just imported. Few installations want multiple holiday groups. If this project is not one of those, the previous All Holidays group needs to be delete. But if you right-click on that group you will discover that Delete is disabled. This is to ensure that there is always at least one holiday group in addition to the No Holidays group. We will now explain deleting the old All Holidays group. Deleting the original All Holidays group node
Warning - The first group must be the No Holidays
If in the course of moving holiday groups the first group is not No Holidays, keep moving groups until it is the first in the list.
Copyright © 2019 OSSI, LLC. All rights reserved. All other registered and unregistered trademarks are the sole property of their respective owners. |